Concrete Slab Waste Factor: How Much Extra Concrete to Order (With 20x20 & Footing Examples)

The job is a 20 ft by 20 ft slab, 4 in thick. Neat volume is length × width × (4/12), divided by 27. Waste is applied after that. This step keeps the 10% order and turns it into the concrete line of the direct cost.

Cross-section of a 20 foot by 4 inch concrete slab20 ft4 in
Section through the 20 ft × 20 ft slab. Thickness is 4 in. The other plan dimension is also 20 ft.

5% or 10% on this slab

Five percent is enough when the grade is even and the chute lands in the forms. Ten percent covers a low spot and what stays in the chute. The step from 5% to 10% on this slab is 0.247 yd³.

WasteOrder80 lb bagsUnder 5 yd³
0%, neat volume4.938 yd³—Yes
5%5.185 yd³234No
10%, carried forward5.432 yd³245No

Concrete subtotal for the bid

5.432 yd³ × $160 per yard = $869.12. That $160 is an example delivered price, not a quote. Bag counts stay on the sheet as the backup if the plant adds a fee: 245 bags of 80 lb at the 10% order.

For a plan with columns, beams, and slabs, use the batch sheet. It deducts in that order so this slab volume is not also counted inside the beams.

Questions

Why does this walkthrough order 10% extra?

Ten percent is the calculator’s starting waste for a slab on grade you have not proved flat. On this 20×20×4 in slab that is 5.432 cubic yards. Five percent would order 5.185 cubic yards if the chute can reach a uniform grade. The rest of the walkthrough keeps the 10% order.

Does the short-load check use the neat volume?

No. It uses the order after waste. The neat 4.938 cubic yards is under a 5 yard threshold. Both the 5% and 10% orders are over it, so this slab is not a short load once waste is included.

Where does the concrete dollar subtotal come from?

The yards are the calculator’s order volume, shown to 0.001 cubic yard. This walkthrough multiplies 5.432 by an example plant price of $160 per yard and rounds half-up to the cent, which is $869.12. Use your plant’s price on the same yards.

Should bag counts replace the ready-mix price?

Not on this slab. The 10% order is 245 bags of 80 lb mix, using QUIKRETE 1101’s 0.60 cubic foot yield, rounded up. That is the comparison if a short-load fee appears. The number carried forward is the ready-mix order, $869.12.